Decade on, bridge awaits completion in Gandabal, Sgr | KNO

Overpass could have averted tragedy, say locals; Technical issues delayed work, will complete it by June this year, says R&B Chief Engineer

Published

on

kno news

Srinagar, Apr 16 (KNO): The delay in construction of the bridge at Gandabal area of Batwara might have not caught the eyes of people so far, but today its absence left the entire Kashmir in shock after a boat capsized and left six people including a mother and her two sons dead on Tuesday morning. The pall of gloom descended the entire Kashmir after a boat capsized this morning. Six persons have died while three as per the government are undergoing treatment as many are still missing. According to the news agency—Kashmir News Observer (KNO), the locals lamented the absence of a bridge within the locality, saying that work was started almost a decade ago, but unfortunately the work was never completed till now, causing huge inconvenience to the inhabitants here. “Despite elapsing over a decade, the construction of the bridge is still in the initial stage, which shows the people have been taken for granted so far. We could only show our anger, but the fact is our pleas and requests fell on deaf ears during these years,” Ali Muhammad, a local resident said with tears in his eyes, wailing over the loss of precious lives in the locality. “One cannot imagine the lethargy the concerned authorities have shown so far. Today’s mayhem could have been avoided in case the bridge would have been constructed on time,” he said, adding that the high and tall claims being made by the administration today would serve no cause, but the construction of the bridge and completing in within the shortest possible time would certainly end the miseries of the people. Sajad Ahmad Naqeeb, Chief Engineer, Roads and Building (R&B) department when contacted told KNO that the delay in construction was due to some technical issues. “Some technical issues have led to the delay in construction of the work. Besides, the delay in getting the funds released also played a spoilsport,” he said, adding that as soon as the water level recedes, the work will be started again and will be completed by June this year—(KNO)

Trending

TOP STORIES2 hours ago

Drug menace can’t be tackled by policing alone, needs holistic approach: Mirwaiz | KNO

TOP STORIES6 hours ago

Delimitation Favoured Only BJP and Its Allies: CM Omar | KNO

TOP STORIES21 hours ago

No safe haven for terror’: Nation observes ‘Op Sindoor’ anniversary | KNO

TOP STORIES21 hours ago

India remains steadfast in its resolve to demolish terror ecosystem: PM Modi on 1 year of Operation Sindoor | KNO

TOP STORIES21 hours ago

Indian forces call out Pakistan nuclear bluff at all: Army | KNO

TOP STORIES21 hours ago

NC to hold district-level conventions, membership drive | KNO

TOP STORIES21 hours ago

Indus Waters Treaty remains in abeyance since Pahalgam terror attack: MEA | KNO

TOP STORIES21 hours ago

Operation Sindoor anniversary: High alert in Jammu | KNO

TOP STORIES21 hours ago

Supporting families of martyrs not policy but solemn duty: DGP Nalin Prabhat | KNO

TOP STORIES21 hours ago

Students, parents protest closure of Jamia Siraj-ul-Uloom in Shopian; demand reopening of institution | KNO

TOP STORIES21 hours ago

‘100-Day Nasha Mukht Abhiyan’ | KNO

TOP STORIES21 hours ago

MP Ruhullah says cannot campaign for those who ‘deceived people’; hints at political decision soon | KNO

TOP STORIES21 hours ago

After Pahalgam, rules tightened for pony operators in Gulmarg | KNO

TOP STORIES21 hours ago

Addiction is medical, psychological condition; treat addicts as patients, not criminals: Mental health expert | KNO

TOP STORIES21 hours ago

Govt mandates JKPaySys for PDD staff salaries | KNO

TOP STORIES21 hours ago

LG hails valour of Armed Forces on Operation Sindoor anniversary | KNO

TOP STORIES21 hours ago

CM Omar chairs meeting to review status of implementation of Budget announcements & key initiatives | KNO

Copyright © 2021